Knowledge

How to calculate SR system capacity for a cable or GIS test?

May 26, 2026 Leave a message

Q: I need to test a 220 kV cable, 8 km long. What SR rating do I need?

 

A: 7-step sizing procedure: determine test requirements → calculate C → estimate L → compute f_res → verify ratings → iterate → finalize.

Step-by-step - 220 kV cable, 8 km:

1. IEC 60840: V_test = 2.0 × 127 kV = 254 kV. Duration 60 min.

2. C ≈ 8 km × 0.2 μF/km = 1.6 μF.

3. Consider 3× 100 kV/2 A reactors in parallel: L=26.7 H, f=24.4 Hz.

4. Current at 254 kV: I = V × 2πf × C = 6.9 A. But 3×2A → 6A total → NOT OK.

5. Upgrade to 3× 100 kV/4 A reactors: total I = 12 A → OK. P_in = 254×6.9/35 = 50 kW.

6. Total weight: 3×450 kg + 200 + 150 + 100 = ~1,800 kg.

 

Sizing summary for common scenarios:

Scenario

V_test (kV)

C (μF)

f (Hz)

Recommended System

33 kV cable, 3 km

48

0.6

45

60 kV/2A ×1, 5 kW

110 kV cable, 5 km

160

1.0

24

200 kV/4A ×2, 20 kW

220 kV cable, 8 km

254

1.6

24

300 kV/4A ×3, 50 kW

400 kV cable, 5 km

330

1.0

48

400 kV/2A ×2, 25 kW

GIS 245 kV, 10 bays

230

0.05

80

300 kV/1A ×2, 5 kW

Generator 100 MVA

28

2.5

45

30 kV/5A, 10 kW

 

Critical reminders:

• +20% margin on reactor voltage rating. +30% margin on current rating.

• If P_in > 100 kW, consider sectional testing (permitted by most standards).

• Actual Q may be lower than estimated - conservative planning avoids field failures.

Send Inquiry